Construction and Major City Projects

Search

Select a Date Range
Detour Map

York Road Reconstruction Update August 2024

Posted on Tuesday, August 06, 2024 01:34 PM

Phase 4: 

We are pleased to report that we have achieved 99% completion on the project. The final touches are currently in progress, with line painting scheduled to begin on Tuesday, August 6th. We are excited to announce that Phase 4 will officially open on Wednesday, August 7th. 

However, please note that if inclement weather prevents the completion of the painting, the road will not open as planned on Wednesday.

Phase 5: 

A new detour will be implemented, directing traffic to Myrtle Ave from York...

Traffic Signal Upgrade Project at Broadway St. & Myrtle Ave

Posted on Tuesday, August 06, 2024 10:00 AM

The Traffic Signal Upgrade Project aims to enhance traffic flow, improve safety for both motorists and pedestrians and modernize the current traffic signal system. This project reflects the Cityโ€™s commitment to maintaining and improving our infrastructure to meet the needs of our growing community.

The tentative start date for this project is August 12, 2024. The project is anticipated to last approximately 4 โ€“ 6 weeks, weather-dependent.

Traffic Accommodation Plan:

To minimize disruption and...

City logo

2024 Asphalt Crack Sealing Program

Posted on Wednesday, July 24, 2024 09:26 AM

The 2024 asphalt pavement crack sealing program is now underway. Crack sealing will be complete over the next four weeks, pending weather conditions and other unforeseen circumstances.

As of July 24, 2024 these streets are going to receive crack sealing:

  • Darlington Street
  • Downtowns Avenues
  • Portions of Smith Street
  • Portions of Betts Avenue
  • Portions of 4th Avenue North
  • Mayhew Avenue
  • York Road East
  • Gladstone Avenue North (if thereโ€™s time left)
  • Other streets may be added to this list if time permits

The...

York Road - Important Road Closure July 19, 2024

Posted on Friday, July 19, 2024 09:15 AM

There will be a ๐˜๐—ฒ๐—บ๐—ฝ๐—ผ๐—ฟ๐—ฎ๐—ฟ๐˜† ๐—ฐ๐—น๐—ผ๐˜€๐˜‚๐—ฟ๐—ฒ ๐—ผ๐—ณ ๐—ฌ๐—ผ๐—ฟ๐—ธ ๐—ฅ๐—ผ๐—ฎ๐—ฑ between 5th Avenue and 2nd Avenue. This closure will begin on ๐—™๐—ฟ๐—ถ๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—น๐˜† ๐Ÿญ๐Ÿต ๐—ฎ๐˜ ๐—ป๐—ผ๐—ผ๐—ป and last until ๐—ฆ๐˜‚๐—ป๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—น๐˜† ๐Ÿฎ๐Ÿญ ๐—ฎ๐˜ ๐—ป๐—ผ๐—ผ๐—ป. Detour map We appreciate your patience and cooperation. Follow along with York Road construction progress, detours, and updates by visiting shapeyourcity.yorkton.ca/yorkroad. Receive alerts by text, email, phone call or through the Voyent Alert app for construction...

York Road Reconstruction Phase 5

Posted on Friday, July 05, 2024 06:16 PM

Phase 4 is 80% complete, completion of this phase is expected as soon as possible, but recent weather has caused some delays. Phase 5 of the York Road Reconstruction will begin Monday, July 8, 2024.

Road Closures along York Road will be extended from First Avenue North to Gladstone Avenue North, with a detour in place on Second Avenue North for local traffic and vehicles accessing business along York Road.  

Phase 4 & 5 Local Access Road Closure and Detour Map

Phase 5 is expected to take...