City Operations Centre Virtual Tour

City Operations Centre

Take a virtual tour of our City Operations Centre! Since ground break in April 2020, this 38,944 sq. ft. facility and 23,498 sq. ft. fleet building became fully operational in August of 2021. There are 52 full-time staff, 2 seasonal and 18 summer students who work out of this location.

This space hosts our Water & Sewer Services, Roadways & Streets, and Traffic Fleet Operations, Parks department, Inventory, Facility Maintenance, Capital Projects and Asset Management Operations.

Construction Progress

 July 27, 2021

Construction of the new City Operations Centre on York Road is coming along well and is on schedule. The majority of work will be completed this summer and a gradual move in of departments, staff and equipment is expected this Fall. The new shop/maintenance area will now have the ability to service our larger equipment inside, and that is one of the big advantages of the new facility. As equipment increases in size and complexity, many of the new equipment pieces were too large to fit into the old facilities for maintenance.


The new facilities will house both the Public Works and Parks Departments staff and all major equipment, consolidating a number of old sites scattered throughout the City. The new facility is scheduled to open in late 2021. 

 March 10, 2021

Construction of the new City Operations Centre on York Road is coming along well and is on schedule. Exterior framing for both the new Maintenance and Office Facility as well as the new Fleet Storage Building is 90 percent complete, while interior framing is nearing 50 percent completion. The roofs of both buildings are scheduled to be completed this month.

December 14, 2020
Construction of the new City Operations Centre on York Road is coming along well and is on schedule. Site preparation was completed earlier this year, and foundation construction is nearing completion. Framing for both the new Maintenance and Administration Facility as well as the new Fleet Storage Building is underway. 
August 24, 2020
The water main underneath York Road between 3rd Avenue and 2nd Avenue has been replaced. Water and sewer installation under York Road between 4th Avenue and 6th Avenue, for the new City Operations Centre is also complete, and York Road is now fully open for normal traffic. 
August 21, 2020
Work is steadily moving ahead on the new City Operations Centre on York Road, with concrete piles and grade beams being installed for the Administration and Shops Building. Some 300 piles are necessary for the entire project with roughly 90 already poured. 

Photo Gallery: City Operations Centre Construction will appear here on the public site.